MALAYSIA’S data centre (DC) boom is not letting up, but the rules meant to gauge its environmental toll are struggling to catch up.
The Environmental Impact Assessment (EIA), the main tool for judging what a big project does to its surroundings, does not apply to DCs in general.
Under the Environmental Quality Act 1974, an EIA is compulsory only for activities listed in a prescribed order. DCs are not listed as a prescribed activity under the 2015 order now in force.
A DC can still be caught, but only if another part of the project falls within a prescribed category.
In other words, whether a DC gets scrutiny depends on how the project is packaged, not on what it does.
Should a facility that leans heavily on the grid and public water be treated so lightly? And what about the worries about the noise that running DCs emanate?
Furthermore, to ease pressure on the grid, the government is pushing new DCs to generate their own electricity. That could mean gas-fired power plants sitting next to the DCs themselves.
Water is heading the same way. The government is also considering requiring DCs near ponds or other water sources to develop their own water supply systems for on-site use.
Whether such a plant or water system would face an EIA of its own would depend on its size and classification, not on the fact that it serves a DC.
That is leaving a lot to chance.
The conversation is going further still. There is some talk that small modular reactors (SMR) could be suitable for deployment to DCs.
To be clear, nothing has been decided about SMRs for DCs. But each new idea for powering DCs, from gas turbines to reactors, brings heavy energy infrastructure closer to where DCs are built.
One environmental group estimates that 51 mapped DCs in Malaysia could emit nearly 44 million tonnes of CO2e (carbon dioxide equivalent) a year, about a fifth of the country’s 2024 emissions.
That is an advocacy group’s estimate and should be read as such, but it shows the scale.
Then there is water. In parts of the United States, communities near big DCs have been drawn into disputes over water quality.
And noise. One analysis of the American buildout calls noise often the most immediate burden for residents.
Add chillers, backup generators and turbines, and residents’ worries are hardly far-fetched.
They are already voicing them. Fifty residents protested a proposed DC in Gelang Patah, Johor, in February 2026, and residents in three Kota Damansara neighbourhoods objected in July 2026, citing traffic, road safety, environmental impact and proximity to homes.
These are the very questions an EIA is meant to answer – before construction rather than after.
The government has not looked away. It says strict environmental conditions have been imposed and the companies involved have accepted them.
DCs are also required to source at least 30% of their power from renewables. And guidance reviewed by Sahabat Alam Malaysia calls for a 50m buffer between a DC and residential lots.
However, conditions agreed with operators are not the same as law. An EIA gives the public something more: a published study, a window to object, and a regulator who must justify the decision.
Civil society groups have asked the Department of Environment (DoE) to amend the Act so DCs become a prescribed activity needing a Schedule 2 EIA, which is open to public objection.
Have other countries building DCs missed this too?
The United States has had an EIA-style law since 1970, the National Environmental Policy Act. The trouble is that it is being eased.
The administration has proposed categorical exclusions that would let AI-related DCs bypass lengthy environmental studies.
China leans on operating standards. New large and hyperscale DCs must achieve certain power usage effectiveness (PUE), and those in national hub nodes must use over 80% green electricity.
Beijing and Shanghai have reportedly capped water use at specific facilities.
Washington, in short, is trading review for speed, while Beijing regulates performance. Malaysia can do both.
Critics will say it could push DC investors to rival countries, and that existing rules and regulations already work. Johor reportedly rejected nearly 30% of DC applications to conserve water and electricity.
An EIA is also not a cure-all. It mainly looks ahead at expected impacts and must be paired with monitoring of what a facility actually does once running.
Predictability is good for business, too. A clear EIA threshold gives serious operators certainty, and lowers the risk of a project being stalled by protests midway.
First, the DoE should list DCs under the EIA Order, with thresholds based on power load, water use and proximity to homes, and make sure on-site power and water facilities fall within the assessment.
Second, assessments should weigh cumulative effects on the grid and water supply in a district. The tenth DC places a very different strain from the first.
Third, the findings should be published, with a proper public comment period.
The Energy Commission is already developing a framework and guidelines on self-generation facilities. It should write environmental review into them from the start.
Time is of the essence. Approvals are running ahead of the rules, and an EIA cannot be applied retroactively to a project already built.
Malaysia wants the world’s computing to live here. Shouldn’t we first check that the neighbours can live with it?