Buffalo Potash has connected all three horizontal wells underground at its Disley Project in Saskatchewan, proving its patented extraction design works in practice.
By showing fluid can reliably move between wells, Buffalo has cleared the prime technical risk that kept it trading at a discount to conventional potash miners.
The next step is pumping potash-rich brine to the surface ahead of a targeted Q1 2027 production start, though the project is still advancing without a formal feasibility study.
If you look at the world’s major potash mines, almost all of them belong to the major players like Mosaic (NYSE:MOS) or K+S. That’s not coincidental. Extracting potash traditionally requires sinking vertical wells and billions of dollars in infrastructure.
That expenditure is typically a barrier to entry that’s kept smaller players on the sidelines.
Buffalo Potash (TSXV:BUFF) is trying to rewrite the playbook on a prime patch of land in the middle of Saskatchewan. A plot that happens to border Mosaic’s Belle Plaine mine and K+S’ Bethune operation. Instead of drilling straight down with expensive vertical wells, Buffalo opted to lay three 565-meter horizontal wells along the base of the deposit. Essentially, one central injector flanked by two producers.
Until this week, that exact setup was one of the reasons investors were staying cautious. Using horizontal wells to dissolve potash underground is the new kid on the block.
Buffalo patented it and dubbed it the “Horizontal Line-Drive” (HLD) method, which has never proven its mettle at this scale. Mostly due to the fact that if the salty water pumped down doesn’t reliably reach the outer wells, the whole model is kaput.
That question was just answered. Following its first well connection on November 23, Buffalo confirmed on the 25th that it’s connected the second producer well, completing an underground loop across all three wells. They’ve also reported pressure and fluid readings matching the subsurface engineering model predictions.
“Connecting the second producer well gives us confidence that what we're seeing underground is repeatable, which is exactly what we set out to demonstrate at this stage," CEO Steve Halabura said, noting the team is now laser-focused on delivering brine to the surface.
So, what happens next (and why does it matter)? Simply put, Buffalo has cleared the engineering hurdle that often snags other runners. From here on, the process relies on the same solution-mining principles used across the region for 60 years which is to circulate brine, dissolve the potash and pump the mineral-rich liquid up for processing.
Before it sees sunlight however, engineers will use an 11-stage packer system. Sounds complicated, but it’s essentially just a series of adjustable internal seals along the wells that pressurize different sections and widen the flow underground.
This is also known as the Mining Plane.
Quick note: Economic figures come from Buffalo’s May 2026 Preliminary Economic Assessment. All the details can be found in Buffalo’s November 25 release.
For investors, the broader story is the proof in the method’s pudding and how the tech can potentially shift Buffalo’s valuation narrative seeing as horizontal solution mining is designed to deliver lower operating costs and a smaller environmental footprint.
Successfully proving it works at the Initial Production Module (IPM) gives Buffalo a repeatable, low-CapEx blueprint to build on.
Once the company hits first production, still targeted for Q1 2027, the IP will be proven for deployment across other spaces at Disley, which can handily lead to scaling to a 1.125 million-metric-ton-per-year target.
There is still plenty of executional risk between an underground connection and commercial cash flow. Buffalo is advancing the starter plant based on assessments rather than formal mineral feasibility reports. This means the real-world recoveries, costs and timelines can still vary wildly. They’re also working to finalize a royalty deal with Altius Royalty Corporation (announced October 22) to fund the remaining site and surface processing build-out.
This article was written independently by the author, without issuer input or approval. Buffalo Potash has a marketing services agreement with Simply Wall St. Details on compensation and other important information can be found in the disclosure and disclaimer at the end of this narrative.
Technical and scientific information in this article is drawn from Buffalo Potash Corp’s news release dated November 25, 2026, which was reviewed and approved by independent Qualified Person Jared Galenzoski, P.Geo., FIMMM, in accordance with National Instrument 43-101. Readers should note that no mineral reserves have been established at the Disley Project, the company’s decision to advance the Initial Production Module is based on a Preliminary Economic Assessment rather than a feasibility study, and its Horizontal Line-Drive mining method has not yet been operated at commercial scale.
Have feedback on this article? Concerned about the content? Get in touch with us directly. Alternatively, email editorial-team@simplywallst.com