NSW appoints Transgrid to deliver and operate Hunter Transmission Project

PUBT·11/22/2026 22:09:29
Listen to the news
NSW appoints Transgrid to deliver and operate Hunter Transmission Project
  • NSW appointed Transgrid as Hunter Transmission Project network operator, responsible for delivery, long-term operations and maintenance.
  • Construction contracts went to Downer for transmission lines and UGL for substations; construction is scheduled to begin next year.
  • The 110-kilometer, 500 kV double-circuit overhead line will add 5 GW of electricity transfer capacity.
  • The project will connect Central-West Orana and New England renewable energy zones, enabling access to cheaper renewable power as coal generation retires.
  • Delivery is expected to create 900 construction jobs; EnergyCo will retain planning and oversight responsibilities.


Disclaimer: This news brief was created by Public Technologies (PUBT) using generative artificial intelligence. While PUBT strives to provide accurate and timely information, this AI-generated content is for informational purposes only and should not be interpreted as financial, investment, or legal advice. TransGrid - Electricity Transmission Ministerial Holding Corporation published the original content used to generate this news brief on November 23, 2026, and is solely responsible for the information contained therein.