Terra (NKLR) Q3 2026 Earnings Call Transcript

The Motley Fool·11/18/2026 21:29:21
Listen to the news
Logo of jester cap with thought bubble.

Image source: The Motley Fool.

DATE

Wed, Nov. 18, 2026

CALL PARTICIPANTS

  • Founding Partner and Managing Director of Global Business Development and Investor Relations - Giordano Morichi
  • Co-Founder and Chief Executive Officer - Alessandro Petruzzi
  • Chief Financial Officer - Katherine Williams

TAKEAWAYS

  • Net Income -- $61 million, reflecting $67.5 million in noncash gains from the fair value adjustment of settled contingent warrant liabilities.
  • Cash and Cash Equivalents -- $82.4 million as of Sept. 30, 2026, representing a decrease from $91.1 million at the end of the previous quarter.
  • Operating Expenses -- $7.1 million, comprising $1.7 million in development costs and $5.4 million in general and administrative expenses.
  • FOAK Project Budget -- $70 million for the 2026 to 2027 period, with approximately one-third of the total budget spent to date.
  • Projected 2027 Cash Burn -- $30 million to $35 million, primarily driven by equipment deliveries and payments to suppliers.
  • Regulatory Budget -- $15 million, specifically allocated for the U.S. Nuclear Regulatory Commission licensing process and safety analysis.
  • Advances to Suppliers -- $2.6 million as of Sept. 30, 2026, representing advance payments for third-party engineering and reactor components.
  • Commercial Pipeline Capacity -- 8 megawatts electric, following a nonbinding letter of intent with Waiken Group for data center deployments in Argentina and Brazil.
  • Customer Down Payment Target -- 25% to 30%, which management intends to secure upon the execution of binding reactor purchase agreements.
  • Remaining Cash Reserve -- $20 million to $30 million, projected to remain available for commercialization activities following the completion of the first reactor.
  • Safety Analysis Progress -- 18 draft Preliminary Safety Analysis Report chapters, which have been completed and shared with the NRC for readiness review.
  • Procurement Coverage -- 80% of materials secured, indicating the percentage of the reactor supply chain currently under contractual commitment.
  • Helium Circulator Testing -- four hours of successful hot running tests, evaluating a critical component design intended for the SOLO reactor.
  • Equipment Commitments -- Down payments made for graphite components from Mersen and air-cooled condensers from SPG Dry Cooling, shifting from planning into funded procurement.
  • Deployment Targets -- 2027 for the first-of-a-kind reactor deployment and 2028 for the start of commercial installations.

Need a quote from a Motley Fool analyst? Email pr@fool.com

RISKS

  • Petruzzi stated, "it's problematic because you cannot sell the reactor to everybody because to sell the reactor, you need to have end user statement for what you are going to use," noting that regulatory requirements for end-user validation complicate the nuclear energy market.

SUMMARY

Terra (NASDAQ:NKLR) reported a transition from engineering preparation to industrial execution during the third quarter of 2026. Management stated that the company is currently procuring equipment for its first microreactor, establishing supply chain partnerships, and advancing customer opportunities toward commercial deployment. The company reported that its current cost estimates for the first-of-a-kind reactor remain aligned with forecasts established 1.5 years ago due to the use of off-the-shelf components. CFO Katherine Williams confirmed that existing cash reserves are sufficient to complete the first reactor deployment in Rock City and prove the design's operational capability.

  • Management noted that 80% of the reactor supply chain is now secured, with procurement activities shifting toward funded equipment production and delivery schedules.
  • Petruzzi stated, "The design of the graphite and stainless steel vessel are really in the end phase, very close to the manufacturing drawings," with manufacturing expected to begin in early 2027.
  • The company completed sharing all 18 draft Preliminary Safety Analysis Report chapters with the NRC, a technical milestone necessary for the planned construction permit application.
  • Management is evaluating the potential to utilize the Part 57 regulatory framework, which is expected to become effective in February 2027 and provides a 12-month licensing pathway.
  • The commercial strategy is transitioning toward structured framework agreements that define reactor quantities, deployment schedules, and milestone-based payment structures.
  • CEO Petruzzi stated, "the realization of the first-of-a-kind Rock City will be a sort of cliff edge effect for our marketing," as the project demonstrates the reactor's integration with industrial applications.

INDUSTRY GLOSSARY

  • SOLO: A micro-modular nuclear reactor designed to generate one megawatt electric of baseload power using a gas-cooled system.
  • PSAR: Preliminary Safety Analysis Report, a comprehensive technical document required by the NRC for nuclear construction permit applications.
  • NRC: U.S. Nuclear Regulatory Commission, the federal agency responsible for nuclear energy safety and licensing.
  • FOAK: First-of-a-kind, referring to the initial deployment of a new technology or design.
  • MWe: Megawatt electric, a unit of measure for the electrical power output of a generation plant.
  • Part 57: A proposed, technology-inclusive regulatory framework for licensing nuclear power plants.
  • LEU: Low enriched uranium, the fuel source used in the SOLO reactor system.
  • EPC: Engineering, procurement, and construction, a common form of contracting arrangement in the energy industry.

Full Conference Call Transcript

Operator: [Audio Gap] 3Q 2026 Business Update Webinar. I'll be operator for today. Before we begin, I'd like to remind you that today's webinar is being recorded and will be made available on Terra's website following the event. [Operator Instructions] It's my pleasure now to hand the call over to Giordano Morichi, Founding Partner and Managing Director of Global Business Development and Investor Relations. Giordano, please begin.

Giordano Morichi: Thank you, operator, and good morning, everyone, and welcome. Joining me today are Alessandro Petruzzi, our Co-Founder and Chief Executive Officer; and Katherine Williams, our Chief Financial Officer. On Monday, November 16, Terra Innovatum filed its quarterly report on Form 10-Q for the quarter ended September 30, 2026, and issued its quarterly financial results and business update. This morning, we also posted our Q3 2026 business update presentation, which we'll refer to during today's call and webcast. All these materials are available in the Investor Relations section of Terra Innovatum's website.

Before we begin, I'd like to remind everyone that today's discussion will include forward-looking statements concerning our business, financial outlook, licensing activities, equipment procurement, manufacturing preparations, potential customer deployments, and commercialization plans. These statements reflect current expectations and assumptions and involve risks and uncertainties that could cause actual results to differ materially. Please refer to our earnings release, most recent Form 10-Q, and other SEC filings for a discussion of these risks. We undertake no obligation to update forward-looking statements, except as required by law. Today, we will discuss progress during the third quarter and subsequent developments through the date of our earnings release.

Our discussion will focus on 3 connected priorities: executing the work required for the first SOLO reactor, advancing qualified customer opportunities toward commercial deployment, and managing capital against defined milestones. With that, please turn to Slide 1 of the presentation. Alessandro, over to you.

Alessandro Petruzzi: Thank you, Giordano, and thank you, everyone, for joining us today. The fundamental message we want to share with you today is that Terra Innovatum is moving from preparation towards execution. We are, in fact, procuring equipment for our first reactor, preparing manufacturing and assembly processes, and advancing customer opportunities towards commercial deployment. Our objective is to build a scalable, profitable business around SOLO. Our first reactor is a foundational technical and regulatory step, while the supplier relationships, manufacturing processes, and customer relationships we established today are intended to support subsequent commercial installations tomorrow. During the quarter, we entered into a procurement agreement with Turboden for steam turbine and generator equipment.

We also advanced NRC pre-application readiness activities and entered into a nonbinding commercial letter of intent with Waiken Group for potential data center deployment in Latin America. Subsequent to the quarter end, we progressed the manufacturing preparation with ATB Riva Calzoni, reported procurement and down payments for major reactor components, and completed sharing all 18 draft preliminary safety analysis report chapters with the NRC for its readiness review. We remain completely focused on technical execution and continue to target our first-of-a-kind reactor deployment in 2027 with commercial deployments beginning 2028, subject to the regulatory approvals and execution milestones. Our priority today is to ensure these work streams advance in parallel.

So, we need to align regulatory and technical milestones, supply chain execution, and customer commitments to support a coordinated and scalable SOLO deployment strategy. Moving now to Slide 2. Our industrial strategy is built around established supply and manufacturing partners. We are working with companies that bring relevant equipment fabrication and industrial capability to the SOLO program. This approach allows us to concentrate our resources on engineering activities, licensing integration, and deployment while drawing on existing manufacturing infrastructure. During the third quarter, our agreement with Turboden advanced procurement of steam turbine and generator equipment for the first SOLO and potential subsequent units.

Following quarter end, we reported that procurement had commenced, and down payments had been made for graphite components from Mersen, turbine and steam generator equipment from Turboden, and air-cooled condenser from SPG Dry Cooling. These steps mark a shift from supplier planning into funded equipment procurement. We are committing capital to critical components and supporting the manufacturing and delivery activities required to build our first SOLO reactor. These are not simply expressions of intent, but actual financial commitments supporting equipment production, supply delivery schedules, and our target FOAK deployment. In October, we progressed the assembly planning, manufacturing procedures, and evaluation of dedicated factory space at ATB Riva Calzoni.

That work supports both the first reactor and the development of repeatable manufacturing processes for future units. We also progressed the equipment testing with Boldrocchi -- helium circulator of the same design intended for SOLO completed a 4-hour hot running test successfully. Two additional helium blowers were being acquired and prepared for nonnuclear system testing and interface evaluation. And this testing helps us evaluate equipment performance and interface ahead of integration into our first reactor. Alongside this commitment, we are also in advancing discussion on the remaining major equipment packages. Each component has its own specification, production requirements, and delivery schedules today.

Our next priority is to coordinate procurement and delivery with the testing and assembling activities required for the first reactor deployment. Please now turn to Slide 3. And, obviously, licensing remains a central part of the development program. During the third quarter, following our July request, the NRC began its initial pre-application readiness assessment. The initial scope included the environmental report and 9 draft preliminary safety analysis report chapters. This process provides an opportunity to receive feedback and identify information needs as we prepare for our formal construction permit application. Subsequent to the quarter end, as planned, we completed sharing all 18 draft PSAR chapters with the NRC for readiness review, announcing these important milestones in early November.

The PSAR is a core element of our planned construction permit application, and completing these chapters represents substantial engineering and safety analysis work for us. This is not NRC approval or acceptance of a formal application, but this is a milestone we have achieved as publicly announced 1 year ago. Our focus now is to address feedback, continue readiness review engagement, and advance the application material required for the next stage. And our engineering and execution team are coordinating this application preparation with the equipment specifications, manufacturing plans, and site requirements. Moving on to Slide 4. We are approaching the first SOLO reactor with subsequent customer deployments in mind.

That means working with suppliers on repeatable manufacturing processes, coordinating equipment specifications and assembly requirements, and evaluating customer opportunities against our delivery capabilities as we prepare for commercial deployment. Our first reactor established a technical regulatory foundation, but our commercial work is focused on converting customer demand into definitive agreements and executable deployment plans. The 2 work streams inform each other. Customer requirements help shape deployment planning, while the progress on licensing, the procurement, and manufacturing help us define credible delivery plans. Across the business, we are advancing 3 near-term priorities in parallel.

First, advancing NRC readiness review work and construction permit application preparation; second, progress major equipment procurement, delivery planning, testing, and assembly preparation; and third, advancing qualified customer opportunities towards definitive agreements with the deployment requirements aligned to our execution capabilities. These are the steps we will use to measure and communicate our progress towards deployment. I will now turn the call over to Kathy to discuss our financial results and the capital allocation.

Katherine Williams: Thank you, Alessandro, and good morning, everyone. I'll ask you to now please refer to Slide 5 of the presentation. Terra Innovatum reported $61 million in net income for the third quarter of 2026, and we ended September 30, 2026, with $82.4 million in cash and cash equivalents compared with the $91.1 million at June 30, 2026. Our financial focus is on managing that capital against the activities that are required to bring the first SOLO reactor into operation. Those activities include licensing, engineering, equipment procurement, supplier commitments, and manufacturing readiness alongside the people and public company infrastructure that's needed to execute our program. As procurement progresses, the timing of supplier payments and equipment deliveries will influence quarterly cash usage.

We are managing those expenditures against the contractual requirements and execution milestones with continued focus on overhead and organizational costs. Advances to suppliers totaled $2.6 million as of September 30, representing advance payments to third-party engineering and component suppliers under the SOLO development agreements. Our total operating expenses were $7.1 million during the third quarter, including $1.7 million of development costs and $5.4 million of general and administrative expenses. As noted, net income was $61 million or $0.55 per basic and diluted share. This included $67.5 million of noncash gains from changes in the fair value of settled contingent warrant liabilities. Our industrial model relies on working with established manufacturing partners.

That allows us to direct capital towards our reactor program, equipment integration activities, while leveraging the existing industrial capabilities. Looking ahead, our priorities are disciplined capital allocation, clear reporting, and maintaining the financial resources needed to support the next stage of execution. With that, I'll turn the call back to Giordano for our commercial update.

Giordano Morichi: Thank you, Kathy. And I'd like everyone now to please turn to Slide 6. Our commercial strategy is focused on moving beyond expressions of interest and translating qualified customer demand into binding reactor purchase agreements and executable SOLO deployment plans. This requires aligning customer power requirements with site readiness, regulatory pathways, technical specifications, and delivery schedules while establishing clear commercial commitments and financial milestones. During the third quarter, we advanced our international commercial pipeline through the nonbinding LOI agreement with Waiken ILW for the potential deployment of up to 8 megawatt electric for the behind-the-meter SOLO capacity supporting DIRECTV Latin America and SKY Brasil data center infrastructure in Argentina and Brazil. Moving to Slide 7, please.

More broadly, the commercial priorities are evolving beyond, again, traditional letters of intent, the LOIs, and the memorandums of understanding, the MOUs, toward structured commercial frameworks that establish the foundation for definitive reactor purchase agreements. These frameworks are designed to define reactor quantities, deployment schedules, contractual responsibilities, payment structures, potentially including upfront reactor reservation deposits and milestone-based payments. As we progress toward the definitive agreements, that we believe this approach can strengthen customer commitment, improve revenue visibility and support future deployments.

Our U.S. commercial platform remains central to the strategy, supporting customer engagement, strategic partnerships, and deployment planning while we continue advancing qualified international opportunities across data center, industrial infrastructure, defense, health care, especially for the radioisotope production and other energy-intensive applications. Ultimately, our objective is not simply to expand the pipeline, but to convert qualified commercial demand into tangible binding orders, secure customer commitments, and predictable deployment schedules. We will continue to provide updates as material commercial milestones are achieved. With that, we move to the questions.

Giordano Morichi: I already see some of the questions from H.C. Wainwright, StoneX, and B. Riley. I will take them as they come in. Thank you, Sameer, for joining us. I'll run it through the first one and continue with the rest. Does the fact that you are making upfront payments as listed on Slide 2 indicate the completeness of the engineering design? Do you expect any change to design that could affect this agreement? So Alessandro?

Alessandro Petruzzi: Actually, all our technical activities are following the schedule and the road map we established 1.5 years ago. So far, the design of the graphite and stainless steel vessel are really in the end phase, very close to the manufacturing drawings, what is called manufacturing drawings. We do not expect any major change in the next few weeks. Our intention is to complete those steps by the end of the year and to start the real work for the manufacturing of those components at the beginning of next year. Minor changes may be still expected on the layout of the plant.

We are still working and cooperating, in particular, with the company that will support us for the site application in Rock City at Admiral Parkway. But no one of them, in our view, is affecting the costs that we foresaw 1.5 years ago. And this, I think -- we think is one of the big achievements we have realized in this 1.5 years.

We -- not only we submit the construction permit in just less than 14 months as announced -- but thanks to the fact that our reactor is made of the off-the-shelf components and the supply chain as is today, our estimation of costs made 1.5 years ago are very in line with the real cost we are now supporting today for procuring those materials and components.

Giordano Morichi: Second question from Sameer, H.C. Wainwright. It still regards the NRC licensing. Nature of commitments, lessons learned, can we leverage the commitments done so far? And there has been any items that take longer than expected? How quickly do we respond to the NRC?

Alessandro Petruzzi: We have a continuous relation with U.S. NRC, at least 2, 3 meetings per week. Unluckily, I can attend only one while my team is attending all, and I would like to attend more. But -- the situation is very fluid. We are now entering a very hectic period because we submit all these -- we advance for the submission those 18 chapters. We should receive the readiness review in the upcoming few weeks in order to stay in line with our construction permit next year. The project itself, the simplicity of the project, the low power, the very limited number of components made the process definitely easy from the technical point of view, from the safety point of view.

But this is just a part of the licensing process. There is additional part of the licensing process, which involve also the construction, the siting and the oversight of the work. This is -- there are topics that we are now really discussing with U.S. NRC -- but again, so far, there is no evidence of any event that may cause a delay in our application. And in particular, this is because, again, our reactor is strongly based on fundamental safety principles of physics, which made the application at the end more straightforward than other reactors.

Giordano Morichi: And then last from Sameer of H.C. Wainwright. Imagine it is December 2028, what would you expect to see at the first-of-a-kind site?

Alessandro Petruzzi: Sorry, Gio, can you repeat, please?

Giordano Morichi: Imagine it is December 2028, what do you expect to see at the first-of-a-kind site in Rock City...

Alessandro Petruzzi: December 2028, we would hope that will be even before December 2028 since we are working really actively to do by end of 2027. This is our goal to bring the reactor in the United States from the factory in Italy and to start the deployment of the reactor in 2027, beginning of 2028 with the operating licensing application. I think this will be a big event for everybody. It will be the first microreactor that is immediately connected to an industrial application because this is also important to outline. The Rock City Admiral Parkway is an industrial site. They need power and our reactor, our first of a kind will provide reactor to this.

So I would imagine a very great day for us for -- and very important because, anyway, we fully understand that the execution is fundamental for the success of this project. We are working very hard, as Giordano say, for the commercial application. We will continue. But from the other side, we understand that the realization of the first-of-a-kind Rock City will be a sort of cliff edge effect for our marketing.

Giordano Morichi: Thank you, Ale. Subash Chandra, StoneX, thank you for joining. Has the second phase of the readiness review started, Alessandro?

Alessandro Petruzzi: The second phase of readiness review will start immediately after it is complete, and we expect that will occur before the end of this year. So we are, again, continuously having meetings with the U.S. NRC. There is complete continuous feedback and answers to this feedback. All our team is involved in this. This is the priority of our team today or the technical team to complete the readiness review. So immediately after this, we will start, and we will continue, I have to say, the work on the operating license, which has been already started.

So the next step, obviously, is to continue in the next 6 months of the year from January to June, July next year to support U.S. NRC for getting the construction permit application.

Giordano Morichi: Perfect. And then one for Kathy, still from Subash. Of the $70 million first-of-a-kind budget, how has the budget been spent so far?

Katherine Williams: So out of the $70 million for the first of a kind, that is where our expenditures have been reflected in the 10-Q because that is all that we're working on right now is the first of a kind. So what you will see is that we began 2026 with a little over $100 million in the bank. At this point, we have the $82 million of cash still in the bank. All of the expenditures, again, have gone for the first of a kind. So for the $70 million, which is 2026 and 2027, we have spent about 1/3 of it. We're still on track with all of our planned expenditures.

And right now, it looks like with the agreements we have with suppliers, we will come in right on budget for the $70 million. And we will still have between $20 million and $30 million remaining to help us with the commercialization efforts.

Giordano Morichi: And part of the regulatory cost of this question related to this, Kathy?

Katherine Williams: I'm sorry, Gio, can you...

Giordano Morichi: How much would it be the regulatory cost within those $70 million?

Katherine Williams: The regulatory cost of that. So we have budgeted around $15 million.

Giordano Morichi: Thank you. We have a few still from Subash on 80% list of material suppliers secured. What is the left 20%? There's a question related to the fuel and the EPC, if it's been secured and is NKLR the EPC. Alessandro?

Alessandro Petruzzi: Fuel is definitely the most important element in the reactor. We are actively finalizing the procurement of the fuel. And for that, the specification for the fuel have been already submitted to our fuel vendor. So we are interacting. As you know, our fuel is low enriched uranium fuel. And the amount of fuel that we need is not a concern for any fuel vendor. The amount that we need is something that the current industry can produce easily in less than 1 day. So there is no problem of getting the fuel. We are obviously interacting with the fuel vendor because -- the focus is the FOAK, but the focus is also the commercialization as well.

So it's a larger discussion that we are having, and this should be completed in the few weeks, I would say, starting from the beginning of year 2028. I don't know the second part. Can you remind me the second part of the question, Giordano?

Giordano Morichi: Regarding the EPC secured.

Alessandro Petruzzi: EPC, we are -- we have started work in Rock City at Admiral Parkway. We have done boreholes. We are started the analysis, the geographical analysis with the analysis of the soil. We are interacting with our EPC for organizing the work on site. And this work is something that is going to grow up in the next, again, a few weeks. We will move from the technical activities related with the construction permit to the activities that are more engineering based related with the siting.

Giordano Morichi: And related to what you just said, Alessandro, does the Rock City require separate site permitting? Or is it part of the construction permit?

Alessandro Petruzzi: No, it's part of the construction permit. We already submitted the environmental safety analysis. We are proceeding. We needed to add elements to this coming from the analysis of the soil, which has been done recently in just a few days ago with positive results. So you will see upcoming news in respect to this very, very soon for the site.

Giordano Morichi: We have one from Ryan Pfingst. Thank you so much for joining from B. Riley. As we're working with the NRC and come closer to submitting the construction permit application, has the NRC given you an indication of a potential review timeline?

Alessandro Petruzzi: Officially, no. Formally, we are having this discussion with U.S. NRC since the engagement -- since the first engagement. We know that our reactor is a very simple design. We know that the reactors which were much more complex than ours terminated the construction permit in less than 18 months, even in 12 months. So even though formally, there is no everything -- definitely no engagement from U.S.

NRC to commit any date, there is a lot of elements, the simplicity of the design, our full support to this activity, our experience in doing licensing that help to understand that we are still on track to get the construction permit in 2027 in the second half of 2027 as it is our goal.

Giordano Morichi: There's a second side to the question. Maybe I can answer that. When do you think customers will be able and move comfortably toward the binding order and when they will likely wait on -- or would they likely wait on completion for the first of a kind? I think having secured, again, 80% of the supply chain progressing constantly with the U.S. NRC has a big advantage for us in terms of the commercialization. All of our customers have been vetted in terms of KYCs and so forth. So the main point is really moving again from the LOIs and the MOUs, which are preliminary contracts. They are nonbinding in nature. They do define the scope, but they're broad.

They are a few pages long. We're getting to a much more robust framework agreement where, again, showcases the timeline, the execution, what happens in case of delivery delays. And I think this is very important. We cannot confirm on how comfortable the customers are moving forward. What we can say is that we have been working thoroughly for the past year. We have a very good engagement with all of our customers and definitely having advanced our licensing and the supply chain securement puts them in a good position to proceed with the next steps of the framework, which will then lead to the binding agreement.

We've planned to have a portfolio in mid-2027 to end of 2027 for the future supply chain demand and growth for the commercialization, but we're working very hard to execute if possible before that. One more question from George Gianarikas from Canaccord Genuity. Thank you for joining. Can you please discuss your updated business model and cost structure per the 10-Q? Kathy?

Katherine Williams: Definitely, we can. So per the 10-Q, our cost structure is progressing to keep our overheads at the lowest level possible since we are planning that everything will be manufactured by someone else. We are not doing any vertical integration of all the supply chain. And we're using existing suppliers, existing manufacturing capabilities. So with that, we keep our overheads lower. The focus getting to the first of a kind is with getting the right engineering and the right supplier contracts in place. That is why we're confident we'll stay within the $70 million that has been reported for the first of a kind.

As we move forward after the first of a kind into commercialization, we still will have money to begin the commercialization, but that's where we'll need to have the firm contracts in place in order to have the advance payments to suppliers and where we have talked about the potential maybe for another capital raise. But that will not happen as a result of first of a kind. We have the cash in hand to complete the first of a kind in Rock City and prove that the design works.

Giordano Morichi: And then can you please discuss the projected cash burn for 2027?

Alessandro Petruzzi: If I may add, sorry, Giordano. So far, the positive aspect of this project, we think is stay in the estimation of the cost because the supply chain exists today. So this gives us an uncertainty of the -- gave us an uncertainty on this estimation, which was very narrow, and we confirmed a lot of them during this 1 year. What I'm going to say is that the $70 million obviously included not only the reactor construction, but all the work for licensing, as Kathy say, and also the work that the people for the Safety Analysis Group and licensing group has to perform, including the site.

The estimation we have for the first -- for the first of commercial reactor are today still aligned with our forecast done time ago, 2 years ago. And because we base those estimation on those costs provided by the supplier. This is to say that in our business model, as we think that we will not integrate the supply chain, at least during the first phase of the commercialization up to 2030, 2031, up to we don't reach a very high number of units per year.

And second, as the costs are today almost known to us -- and third, as we intend to go in the deployment phase with advance payment, as Kathy said, this means that, basically, our business model will be such that we will not be in loss in the first phase of commercialization. This is our goal.

Giordano Morichi: Thank you, Ale. Bear with me. Can we please discuss the mechanics of coordination with Part 57 year-end 2026? And do you expect to get this pushed into 2027?

Alessandro Petruzzi: This is -- this will be a nice gift for us and for all the nuclear microreactor ecosystem. Part 57 now has been, as far as I understand, moved to be effective in February 2027. The process in Part 57 starts to become clear, more clear to everybody. And the time to get the license under Part 57, as you know, is 12 months. So this is a very important point of internal discussion inside the team because whenever the Part 57 will become executive, several options will be available to us, definitely continuing the licensing under Part 50, but also the evaluation of to start in parallel a Part 57 commercial license.

This is what we are also organizing internally, creating a team that already have as goal, the activity related with Part 57 more than the Part 50.

Giordano Morichi: And one more from George, Canaccord, for Kathy, a little bit more in depth on the cash burn for 2027 on the...

Katherine Williams: Certainly. The expected cash burn for 2027 is between $30 million and $35 million. It's primarily directed now at -- for 2027 with the suppliers to have the deliveries of the equipment that's needed.

Giordano Morichi: We have a couple of more questions, and I believe this will conclude the Q&A. We have one from Graham Tanaka. "Which specific milestones are needed to achieve actual binding orders, and what size of advance payments could come from customers on receiving those binding orders?" What today we're discussing is 25% to 30% down payments on the estimated cost of the reactor, which we have announced throughout the year. These are the numbers we're working through. Of course, these are the stages where we're negotiating those framework agreements. They are very detailed documents as discussed. We'll be able to provide more information when there's advancements on those. On Richard Longgreen, Goldman Sachs, "Great progress, congratulations." Thank you very much.

What is the current -- currently the biggest bottleneck preventing Terra Innovatum from transitioning from the promising technology platform to a commercially deployable and revenue-generating business? So bottleneck on execution and what is the realistic timeline to resolve it? I will leave this to Alessandro to start.

Alessandro Petruzzi: Yes. I may start, and then everybody, Kathy and Gio, can comment. I think this is part of the innovation. Yesterday night, I was discussing with some of people that you need to go back maybe to the time when there was the big cell phone, the huge one and who can get this? Rich people or only people that really can need this reactor, but this cell phone. And -- but for nuclear, for a nuclear product, maybe the situation is a little even more complicated than this because it's nuclear. So there is still something -- some elements more.

It's problematic because you cannot sell the reactor to everybody because to sell the reactor, you need to have end user statement for what you are going to use. You cannot sell just to the first person in the street. So there is some elements that make this market a little more complex than any other market. This is to say what that advancing the work and watching the steps that we are executing in terms of safety analysis report, in terms of supply chain is something that can create confidence in the market to arrive at the end to the final stage of transforming the nonbinding and binding, but it's an evolution process.

We are confident of our work, and we will continue to work as much as we can to transform those nonbinding in binding. But from the other side, I think it is the execution itself is the realization of the FOAK on site. It's the time when the FOAK will reach the site in Illinois or even when the vessel will be ready at ATB that will be a sort of cliff edge in the behavior of the customer. And in terms of timelines -- we are still on our timelines. We want to become commercial by 2028.

Giordano Morichi: Kathy, any remarks on this? Any bottlenecks that you see on your front? And how do we get to this revenue-generating?

Katherine Williams: That will certainly be an exciting day for all of us when we get there. The only bottleneck would be having the customers believe in the product, getting their agreement that, yes, this is what they want and where we will go forward. And of course, we're continuing to do that every month as we advance with the process with the NRC and that we will get the licensing in place, everything that's required, and it will perform the way that we have said that it will perform, which is why the first of a kind at Rock City is so important.

A lot of the discussions we are having with potential customers is focusing now on, okay, how do we structure a contract that will allow us to go ahead and say, we want this product. But we also want some assurance that if this gets delayed or this gets delayed, recognizing we're dealing with a government regulation, that this will be what the secured price still is. And it's getting more favorable with every discussion we have because we have stuck to our plan. We have delivered exactly what we said we were going to deliver and met all the milestones.

As Alessandro says, we have good security in what the cost of the reactor is going to be at this point. We have placed the majority of contracts needed with suppliers. So we know what the price is. Again, it has been secured. So it's working with the customers to get their confidence that now is the time to place the order. And that's part of our big focus, as you know, Gio, that we're trying to secure those orders for proof that we are commercially ready.

Giordano Morichi: And I think if I can detail what Kathy said, one item that I really would like the company -- sorry, the investors and the analysts to focus on, and I think you appreciated being part of this call is the fact that Terra went to the market with the R&D done with a very strong engineering background. We're a crawl-walk approach company. We're very reliable in terms of deliveries on the U.S. NRC as we've demonstrated -- what we said we would do, we have done, we're excelling at.

And thanks to that, thanks to the technology that is the underlying element of the whole structure of the whole machine, we're able to get to these framework agreements, as Kathy explained, and we're able to discuss some of the preliminary details, which would then lead to the binding aspect. So I think we're in a strong position to continue this process with the customers that have been vetted again. And hopefully, we'll give some good news soon. But we're working very diligently on these items. And I think this is the end of the Q&A with all the questions. I would really like to thank everyone joining the call today, investors, analysts, and all of the Terra family.

Again, thank you, operator, and I will turn now to Alessandro for the closing remarks.

Alessandro Petruzzi: Thank you, Gio. So please turn to Slide 8. As a summary, during the quarter and subsequent weeks, we advanced the licensing preparation, equipment procurement, manufacturing readiness, and defined potential customer opportunity with Waiken ILW. From here, the milestones to track are basically 3. First, the readiness review feedback with the advancement of our construction permit application as well as the initial preparation for our operating licensing application; second, the procurement of remaining major equipment and site readiness work; and third, the conversion of qualified customer opportunities into binding reactor purchase agreements with the reservation deposits and milestone-based payment.

Together, these milestones will demonstrate progress on 2 connected objectives: bringing our first SOLO reactor towards deployment; and, second, establishing the industrial and commercial foundation for a scalable business. So, we will continue to manage capital against these priorities and communicate material progress as it occurs. Thank you so much for your continued interest in Terra Innovatum for joining us today. And with that, operator, we conclude the call.

Operator: Thank you, everybody. Thank you, Terra team, for joining us today. Thank you, audience, for joining us as well. This concludes today's webinar, and you may disconnect at your convenience. Thank you. Have a great day.

Giordano Morichi: Thank you, everyone.

This article is a transcript of this conference call produced for The Motley Fool. While we strive for our Foolish Best, there may be errors, omissions, or inaccuracies in this transcript. Parts of this article were created using Large Language Models (LLMs) based on The Motley Fool's insights and investing approach. It has been reviewed by our AI quality control systems. Since LLMs cannot (currently) own stocks, it has no positions in any of the stocks mentioned. As with all our articles, The Motley Fool does not assume any responsibility for your use of this content, and we strongly encourage you to do your own research, including listening to the call yourself and reading the company's SEC filings. Please see our Terms and Conditions for additional details, including our Obligatory Capitalized Disclaimers of Liability.