Bernstein: After the midterm elections, US AI data center construction did not stop, but the next wave of orders will have to wait until the second half of 2027

Zhitongcaijing·11/17/2026 12:57:19
Listen to the news

The Zhitong Finance App learned that recently, Bernstein released a research report on the data center industry chain of US hyperscale cloud vendors. The bank conducted channel interviews with the heads of data center architectures and procurement of the five leading cloud vendors, believing that regulation and local resistance brought about by the US midterm elections may become new constraints on AI infrastructure; projects that have already been implemented and advanced are basically unaffected, but the new round of new construction projects faces huge uncertainty in site selection and pace, and there may be a phased gap in cooling and power equipment orders from the fourth quarter of 2026 to the first quarter of 2027, but this is only a delay in orders rather than a complete disappearance of demand.

The bank pointed out that after the current midterm elections in the US, there is a risk that license approval will be suspended, local people's opposition to data centers has increased, and the market has begun to discuss whether political factors will become a new bottleneck in US data center construction. Judging from interview feedback, projects that have received approval, completed funding, and are under construction are basically guaranteed. It is expected that production capacity plans to be put into operation from 2027 to early 2028 will basically be locked down, and hyperscale cloud vendors will not abandon projects under construction that have already been promised.

The bank expects that in the next 12 to 18 months, the earnings per share of related equipment companies will hardly be adversely affected. The uncertainty brought about by the midterm elections will mainly affect subsequent new green space construction projects rather than existing construction projects.

The real variables focus on future new construction projects: hyperscale cloud vendors generally enter a wait-and-see cycle, waiting for the new government's policies to be clear, with a particular focus on Texas policy trends. Georgia, Ohio, Pennsylvania and other states are also included in the risk watch list.

The surveyed companies are simultaneously evaluating alternative construction areas, with North Dakota, New Mexico, Arizona, and Colorado being the key targets. Bernstein stressed that the overall demand for computing power in the industry has not disappeared; enterprises are only prioritizing finding additional production capacity in regions that simultaneously meet policy acceptance, land supply, and electricity resources. The core conflict has changed from “whether to build” to “where to build and when to start construction.”

Driven by the uncertainty of site selection and time rhythm, orders for data center cooling and power supporting equipment may face a phased gap. The bank indicated that there is a possibility that equipment procurement will weaken from the fourth quarter of 2026 to the first quarter of 2027 until the dust settles on the relevant legislation.

The opinions of the interviewees were divided. Some of the executives interviewed said that before there is sufficient certainty, equipment orders will be carefully placed to avoid inventory backlogs where equipment procurement is completed but construction cannot be carried out; other companies will not significantly change the pace of order placement, but they will seek more relaxed contract terms from equipment suppliers, such as cancellation penalties for order reductions.

Bernstein defines this phenomenon as deferred demand rather than demand destruction. After the policy approval framework is clear and the site selection for additional production capacity is finalized, the postponed orders are expected to be released, and it is expected that orders will rebound around the second half of 2027.

In order to resolve resistance at the local level, “Be a Good Neighbor in the Community” has evolved from a bonus option to a standard operating manual for data center development. Hyperscale cloud vendors are increasing investment in territorial operations, including investment in local schools, workforce training, and public infrastructure. Some projects are also considering bearing a portion of utility costs while actively disclosing water and electricity usage to the community.

Relevant measures were initiated before the election, and related actions will become more normalized in the future. The bank believes that this type of investment will not fundamentally damage the project's economic return model, but enterprises still need to continuously measure how much supporting costs actually need to be paid.

In addition to self-construction, the importance of hosted data centers and new cloud vendors (Neocloud) has increased significantly. According to interview feedback, the share of computing power of third-party hosting and new cloud vendors has increased from 30-40% two to three years ago to more than 50%. In an environment where it is more difficult to approve new green space projects, the value of those ready-made computing power assets that have locked in electricity supply and obtained construction permits has further increased. Many cloud vendors are cooperating with service providers such as Crusoe to fill the self-built production capacity gap through mature computing power from third parties; the industry generally predicts that in order to hedge against future capacity risks, hosting and new cloud resources with ready-made conditions will be quickly leased out.

Combining information from all five expert interviews, Bernstein concluded that there are sufficient safety pads for existing projects under construction, yet uncertainty about next-generation green space expansion plans continues to accumulate. Short-term equipment orders will be under pressure, but the overall direction of AI computing power construction has not been reversed, and the industry is more about adjusting the implementation position and timing of progress.

At the investment level, the bank distinguishes investors' strategies for different holding periods. For medium- to long-term investors who can withstand fluctuations of 2 to 3 quarters or more, institutions maintain the original preferences of the data center sector, and current valuations are attractive for earnings per share growth; investors with short holding periods should be moderately cautious. Currently, the market does not have sufficient pricing policies and potential impacts caused by delays in approval. The bank specifically pointed out that being cautious is not equal to being bearish; policy evolution will bring the risk of two-way stock price fluctuations.