Selkirk Copper completes 54,579-meter Phase 2 drilling program at Minto

PUBT·11/16/2026 12:09:37
Listen to the news
Selkirk Copper completes 54,579-meter Phase 2 drilling program at Minto
  • Selkirk Copper completed Phase 2 drilling at its Minto project in Yukon, totaling 54,579 meters across 223 holes.
  • Results will inform an updated mineral resource estimate planned for March 2027; they are not included in existing resource estimates or economic assessments.
  • Minto North drilling returned 5.97% copper equivalent over 4.9 meters, while Area 118 step-out drilling extended mineralization beyond previous resource limits.
  • A feasibility study began in November 2026, targeting improved economics relative to the September preliminary economic assessment.
  • Amended permit applications are scheduled for submission to the Yukon Environmental and Socio-economic Assessment Board in December 2026.


Disclaimer: This news brief was created by Public Technologies (PUBT) using generative artificial intelligence. While PUBT strives to provide accurate and timely information, this AI-generated content is for informational purposes only and should not be interpreted as financial, investment, or legal advice. Selkirk Copper Mines Inc. published the original content used to generate this news brief via Newsfile (Ref. ID: 202611160700NEWSFILECNPR____20261116_324087_1) on November 16, 2026, and is solely responsible for the information contained therein.