PTPP’s Medan Oncology Center Reaches 92.43% Completion, Ahead of Target

PUBT·11/10/2026 08:01:38
Listen to the news
PTPP’s Medan Oncology Center Reaches 92.43% Completion, Ahead of Target
  • PTPP's Oncology Center at RSUP H. Adam Malik in Medan reached 92.43% construction completion in November 2026.
  • Progress exceeded the 90.16% target by 2.27 percentage points.
  • The Rp 334.08 billion contract covers 730 days of construction starting December 10, 2024.
  • The facility will consolidate cancer services, with capacity for 200 inpatient beds and three operating rooms.


Disclaimer: This news brief was created by Public Technologies (PUBT) using generative artificial intelligence. While PUBT strives to provide accurate and timely information, this AI-generated content is for informational purposes only and should not be interpreted as financial, investment, or legal advice. PT Pembangunan Perumahan (Persero) Tbk published the original content used to generate this news brief via Indonesia Stock Exchange (IDX) (Ref. ID: 32184349) on November 10, 2026, and is solely responsible for the information contained therein.