Mercury starts construction of 192 MW Puke Kapo Hau wind farm in New Zealand

PUBT·11/10/2026 01:06:29
Listen to the news
Mercury starts construction of 192 MW Puke Kapo Hau wind farm in New Zealand
  • Mercury on November 10, 2026, began construction of its $506 million Puke Kapo Hau wind farm in Otago.
  • The second stage of the Mahinerangi wind farm will add 40 turbines with 192 MW of installed capacity.
  • The combined development will comprise 52 turbines with total installed capacity of 228 MW, making it New Zealand's largest wind farm.
  • Expected annual generation of about 648 GWh will support growing electricity demand, including from Datagrid's planned Southland data center.
  • Construction will take about two years, with up to 200 people working on the project daily at its peak.


Disclaimer: This news brief was created by Public Technologies (PUBT) using generative artificial intelligence. While PUBT strives to provide accurate and timely information, this AI-generated content is for informational purposes only and should not be interpreted as financial, investment, or legal advice. Mercury NZ Limited published the original content used to generate this news brief on November 09, 2026, and is solely responsible for the information contained therein.