Orvana Minerals targets completion of Don Mario ramp-up by end-December 2026

PUBT·11/09/2026 11:01:58
Listen to the news
Orvana Minerals targets completion of Don Mario ramp-up by end-December 2026
  • Orvana Minerals expects to complete the Don Mario Oxides Stockpile Project ramp-up in Bolivia by the end of December 2026.
  • Throughput targets are approximately 1,400 tonnes daily in November, rising toward 1,700 tonnes daily in December, subject to satisfactory operating performance.
  • October ore processing reached 17,428 tonnes, with daily throughput averaging more than 900 tonnes during the final week.
  • Bolivian subsidiary EMIPA fully repaid EMIPA Bonds I at maturity on November 7, 2026.
  • EMIPA Bonds II mature February 19, 2027; financial covenant breaches remain subject to a cure period.


Disclaimer: This news brief was created by Public Technologies (PUBT) using generative artificial intelligence. While PUBT strives to provide accurate and timely information, this AI-generated content is for informational purposes only and should not be interpreted as financial, investment, or legal advice. Orvana Minerals Corp. published the original content used to generate this news brief via CNW (Ref. ID: 202611090600CANADANWCANADAPR_C2567) on November 09, 2026, and is solely responsible for the information contained therein.