Namkwang Engineering & Construction Extends Uijeongbu Apartment Contract to October 2028
  • Namkwang Engineering & Construction extended completion of its Uijeongbu Ujeong A-2BL apartment project to Oct. 31, 2028, from May 15, 2028.
  • The corrected contract moves the start date to Dec. 31, 2025, from June 30, 2025.
  • The contract value is KRW 53.12 billion, equivalent to 10.53% of 2024 revenue.


Disclaimer: This news brief was created by Public Technologies (PUBT) using generative artificial intelligence. While PUBT strives to provide accurate and timely information, this AI-generated content is for informational purposes only and should not be interpreted as financial, investment, or legal advice. Namkwang Engineering & Construction Co. Ltd. published the original content used to generate this news brief via DART, the regulatory disclosure system operated by the South Korea Financial Supervisory Service (FSS) (Ref. ID: 20261021800259), on October 21, 2026, and is solely responsible for the information contained therein.