Silver Tiger Metals' El Tigre Project Remains on Track for First Pour in December 2027

PUBT·10/20/2026 11:03:56
Listen to the news
Silver Tiger Metals' El Tigre Project Remains on Track for First Pour in December 2027
  • Silver Tiger Metals’ El Tigre project in Sonora, Mexico, remains on schedule for commissioning and first pour in December 2027.
  • Capital spending totals approximately USD 24 million, with USD 72 million committed against the USD 124 million construction budget.
  • Cash on hand of approximately USD 120 million covers the remaining USD 100 million needed to complete construction.
  • Detailed engineering is 70% complete; procurement of all long-lead equipment is complete.
  • Earthworks for heap leach, ponds and processing platforms are 14% complete; crusher and ancillary building platforms are 23% complete.


Disclaimer: This news brief was created by Public Technologies (PUBT) using generative artificial intelligence. While PUBT strives to provide accurate and timely information, this AI-generated content is for informational purposes only and should not be interpreted as financial, investment, or legal advice. Silver Tiger Metals Inc. published the original content used to generate this news brief via ACCESS Newswire (Ref. ID: 202610200700ACCESSWRNAPR_____1238816) on October 20, 2026, and is solely responsible for the information contained therein.