voestalpine completes Donawitz electric arc furnace installation under greentec steel decarbonization plan

PUBT·10/12/2026 09:35:00
Listen to the news
voestalpine completes Donawitz electric arc furnace installation under greentec steel decarbonization plan
  • voestalpine completed installation of an electric arc furnace at Donawitz under its greentec steel decarbonization program.
  • Major construction and installation work at Linz and Donawitz scheduled to finish in 2026, with first melts planned in H1 2027.
  • Donawitz expansion targeted by 2030, subject to funding, to enable a full shift to electrified steel production.
  • Planned expansion investment totals about EUR 100 million, focused on power supply upgrades, scrap logistics expansion, secondary metallurgy capacity.


Disclaimer: This news brief was created by Public Technologies (PUBT) using generative artificial intelligence. While PUBT strives to provide accurate and timely information, this AI-generated content is for informational purposes only and should not be interpreted as financial, investment, or legal advice. voestalpine AG published the original content used to generate this news brief on October 12, 2026, and is solely responsible for the information contained therein.