HD Hyundai raises contract value for Boryeong power plant coal yard enclosure project to KRW 338.5 billion

PUBT·10/06/2026 07:30:38
Listen to the news
HD Hyundai raises contract value for Boryeong power plant coal yard enclosure project to KRW 338.5 billion
  • HD Hyundai corrected a disclosure to raise the contract value for the Boryeong Power Units 1–8 coal yard enclosure project.
  • Contract amount revised to KRW 338.5 billion from KRW 333 billion; sales ratio adjusted to 8.64% from 8.5%.
  • The contract runs from Sept. 2, 2021 to Aug. 31, 2027; counterparty listed as Korea Midland Power.


Disclaimer: This news brief was created by Public Technologies (PUBT) using generative artificial intelligence. While PUBT strives to provide accurate and timely information, this AI-generated content is for informational purposes only and should not be interpreted as financial, investment, or legal advice. HD Hyundai Co. Ltd. published the original content used to generate this news brief via DART, the regulatory disclosure system operated by the South Korea Financial Supervisory Service (FSS) (Ref. ID: 20261006800417), on October 06, 2026, and is solely responsible for the information contained therein.