  • Applied Digital brought an additional 75 MW of AI data center capacity online at Polaris Forge 1 via three 25 MW halls.
  • The delivery completed Building 2 at 150 MW, lifting fully operational critical IT load at the campus to 250 MW.
  • The fully leased campus is contracted to deliver 400 MW at full buildout, implying 150 MW remaining to come online.


Disclaimer: This news brief was created by Public Technologies (PUBT) using generative artificial intelligence. While PUBT strives to provide accurate and timely information, this AI-generated content is for informational purposes only and should not be interpreted as financial, investment, or legal advice. Applied Digital Corporation published the original content used to generate this news brief via GlobeNewswire (Ref. ID: 202610020800PRIMZONEFULLFEED9838473) on October 02, 2026, and is solely responsible for the information contained therein.