  • Perpetua Resources reported progress on early works at its Stibnite Gold Project in Idaho, including the Burntlog Route access road.
  • Permanent worker housing moved into foundations work, with module installation planned as construction advances into the fall.
  • Powerline upgrade procurement progressed, with substations and transformers ordered to supply grid power for the processing facility.
  • Exploration drilling exceeded 10,000 meters in August, prompting an expanded program that will run into the fall.
  • Four rigs are drilling gold-antimony targets, with tungsten mineralization also identified; assay results are expected as they are completed.


Disclaimer: This news brief was created by Public Technologies (PUBT) using generative artificial intelligence. While PUBT strives to provide accurate and timely information, this AI-generated content is for informational purposes only and should not be interpreted as financial, investment, or legal advice. Perpetua Resources Corp. published the original content used to generate this news brief via CNW (Ref. ID: 202609280629CANADANWCANADAPR_C6480) on September 28, 2026, and is solely responsible for the information contained therein.