-+ 0.00%
-+ 0.00%
-+ 0.00%

Montage Gold achieves first gold pour at Côte d’Ivoire Koné mine ahead of schedule

PUBT·09/27/2026 22:18:29
Listen to the news
Montage Gold achieves first gold pour at Côte d’Ivoire Koné mine ahead of schedule
  • Montage Gold achieved first gold pour at its Koné mine in Côte d’Ivoire on Sept. 26, 2026, ahead of Q2 2027.
  • The pour yielded about 1,140 ounces; more than 400,000 tonnes of ore have been processed since Sept. 8, 2026.
  • Oxide circuit ramp-up targets commercial production in Q4 2026; hard-rock comminution circuit completion remains slated for Q2 2027.
  • Construction began in December 2024; the build created about 3,600 jobs, with over 95% filled by nationals.
  • A 130,000-meter 2026 drilling program is underway; probable reserves in the 2024 feasibility study were 4.01 Moz at 0.72 g/t Au.


Disclaimer: This news brief was created by Public Technologies (PUBT) using generative artificial intelligence. While PUBT strives to provide accurate and timely information, this AI-generated content is for informational purposes only and should not be interpreted as financial, investment, or legal advice. Montage Gold Corp. published the original content used to generate this news brief via GlobeNewswire (Ref. ID: 202609271818PRIMZONEFULLFEED9834667) on September 27, 2026, and is solely responsible for the information contained therein.