Talisker drops laser sorter from Bralorne gold project plan, cuts capex by about CAD $4 million

PUBT·09/17/2026 11:01:56
Listen to the news
Talisker drops laser sorter from Bralorne gold project plan, cuts capex by about CAD $4 million
  • Talisker reported final ore-sorting tests for the Bralorne Gold Project, selecting an XRT-only circuit for its direct-shipping phase.
  • XRT sorting rejected 57% to 67% of waste, lifted gold grades by 2.0x to 2.5x, with 84% to 87% gold recovery.
  • Adding a downstream laser sorter pushed recovery above 95% but diluted product grade, raising shipped mass and weakening DSO economics.
  • Plant design drops the laser sorter, cutting capital costs by about CAD 4 million while lowering operating costs and simplifying operations.


Disclaimer: This news brief was created by Public Technologies (PUBT) using generative artificial intelligence. While PUBT strives to provide accurate and timely information, this AI-generated content is for informational purposes only and should not be interpreted as financial, investment, or legal advice. Talisker Resources Ltd. published the original content used to generate this news brief via GlobeNewswire (Ref. ID: 202609170700PRIMZONEFULLFEED9828731) on September 17, 2026, and is solely responsible for the information contained therein.