Andritz wins high double-digit million-euro contract to refurbish Romania’s Râul Mare Retezat hydropower plant

PUBT·09/17/2026 07:07:47
Listen to the news
Andritz wins high double-digit million-euro contract to refurbish Romania’s Râul Mare Retezat hydropower plant
  • Andritz won a high double-digit million-euro order in Q3 2026 to refurbish Hidroelectrica’s 335-MW Râul Mare Retezat hydropower plant.
  • Scope covers electromechanical equipment for a full modernization, including turbines, generators, automation, auxiliary systems; installation under Andritz supervision.
  • Upgrade targets a 12% capacity lift to 376 MW, restoring output constrained to about 200 MW by existing equipment limits.
  • Project awarded within a COBRA Instalaciones-led consortium; completion expected by 2031.


Disclaimer: This news brief was created by Public Technologies (PUBT) using generative artificial intelligence. While PUBT strives to provide accurate and timely information, this AI-generated content is for informational purposes only and should not be interpreted as financial, investment, or legal advice. Andritz AG published the original content used to generate this news brief on September 17, 2026, and is solely responsible for the information contained therein.