Liberty Gold posts Black Pine feasibility study with after-tax NPV(5%) of US$ 2.4 billion at US$ 3,250/oz gold

PUBT·09/08/2026 10:01:22
Listen to the news
Liberty Gold posts Black Pine feasibility study with after-tax NPV(5%) of US$ 2.4 billion at US$ 3,250/oz gold
  • Liberty Gold released a feasibility study for its 100%-owned Black Pine oxide gold project in Idaho.
  • Base case at US$ 3,250/oz: after-tax NPV(5%) US$ 2.4 billion; IRR 60.5%; payback 2 years.
  • Plan outlines a 16-year open-pit, run-of-mine heap-leach operation; average payable output 177,000 oz/year; AISC US$ 1,566/oz.
  • Initial capital estimated at US$ 411.4 million; probable mineral reserve 4.04 million oz gold.
  • Sensitivity: at US$ 2,500/oz, after-tax NPV(5%) US$ 1.22 billion; IRR 33.4%; at US$ 4,500/oz, NPV US$ 4.34 billion; IRR 104.3%.


Disclaimer: This news brief was created by Public Technologies (PUBT) using generative artificial intelligence. While PUBT strives to provide accurate and timely information, this AI-generated content is for informational purposes only and should not be interpreted as financial, investment, or legal advice. Liberty Gold Corp. published the original content used to generate this news brief via GlobeNewswire (Ref. ID: 202609080600PRIMZONEFULLFEED9821942) on September 08, 2026, and is solely responsible for the information contained therein.