Electricity North West hosts Ofgem chair, MP at £17 million Blackpool substation upgrade site visit

PUBT·08/24/2026 14:58:16
Listen to the news
Electricity North West hosts Ofgem chair, MP at £17 million Blackpool substation upgrade site visit
  • Electricity North West hosted Ofgem chair Mark McAllister, MP Andrew Snowden at its Peel Road, Blackpool, 132,000-volt substation site.
  • Delegation reviewed progress on a GBP 17 million overhaul, expected to run through 2027, aimed at doubling capacity.
  • Upgrade supports supply for more than 85,000 properties, adds headroom for regional growth, electrification, renewable connections.
  • Project forms part of a load re-opener submission filed with Ofgem in January 2025.


Disclaimer: This news brief was created by Public Technologies (PUBT) using generative artificial intelligence. While PUBT strives to provide accurate and timely information, this AI-generated content is for informational purposes only and should not be interpreted as financial, investment, or legal advice. Electricity North West Limited published the original content used to generate this news brief on August 24, 2026, and is solely responsible for the information contained therein.