Collective Mining targets Q4 2026 start for Guayabales exploration adit construction

PUBT·08/18/2026 11:07:43
Listen to the news
Collective Mining targets Q4 2026 start for Guayabales exploration adit construction
  • Collective Mining kept its Guayabales exploration adit on track for construction start in Q4 2026, with all permits secured.
  • Completed a 1.8-kilometer access road from the Pan American Highway to the planned portal; portal platform work begins immediately.
  • Underground drilling slated for Q1 2027 at the Trap East target, targeting faster testing from improved drilling angles.
  • Trap Main System drilling targeted for H2 2027; Plutus target and Apollo Ramp Zone drilling scheduled for 2028.


Disclaimer: This news brief was created by Public Technologies (PUBT) using generative artificial intelligence. While PUBT strives to provide accurate and timely information, this AI-generated content is for informational purposes only and should not be interpreted as financial, investment, or legal advice. Collective Mining Ltd. published the original content used to generate this news brief via EDGAR, the Electronic Data Gathering, Analysis, and Retrieval system operated by the U.S. Securities and Exchange Commission (Ref. ID: 0001279569-26-000799), on August 18, 2026, and is solely responsible for the information contained therein.