  • Blue Moon Metals outlined a development plan to bring its brownfield critical-metals portfolio in the US and Norway into production.
  • Nussir copper project in Norway in construction; feasibility study basis; commercial production targeted for H1 2028 at about 21,000 tpa CuEq.
  • Springer tungsten mine and 1,200 tpd mill in Nevada targeted for restart in Q4 2027; internal preliminary restart cost estimate US$50 million.
  • Apex germanium-gallium mine in Utah targeting mine re-permit in Q2 2027; mine reopening planned in H2 2027.
  • Capital snapshot: about 105 million shares outstanding; market cap US$580 million; cash US$141 million; debt US$12.5 million; enterprise value US$449 million.


Disclaimer: This news brief was created by Public Technologies (PUBT) using generative artificial intelligence. While PUBT strives to provide accurate and timely information, this AI-generated content is for informational purposes only and should not be interpreted as financial, investment, or legal advice. Blue Moon Metals Inc. published the original content used to generate this news brief on August 11, 2026, and is solely responsible for the information contained therein.