TAESA wins CETESB installation license for Juruá transmission project in São Paulo

PUBT·08/11/2026 00:13:33
Listen to the news
TAESA wins CETESB installation license for Juruá transmission project in São Paulo
  • TAESA secured an installation license from São Paulo’s CETESB for its Juruá transmission project, clearing the way to start construction.
  • Juruá is 100% TAESA-controlled, won as lot 3 in Brazil’s transmission auction No. 02/2024.
  • Project economics: total RAP of BRL 20.5 million for the 2026-2027 cycle; ANEEL capex of BRL 244 million.
  • Scope includes a 440/138 kV Estância substation in Barra Bonita, São Paulo; 1.2 km extension; energization deadline set for June 2028.


Disclaimer: This news brief was created by Public Technologies (PUBT) using generative artificial intelligence. While PUBT strives to provide accurate and timely information, this AI-generated content is for informational purposes only and should not be interpreted as financial, investment, or legal advice. TAESA - Transmissora Aliança de Energia Elétrica SA published the original content used to generate this news brief on August 11, 2026, and is solely responsible for the information contained therein.