Ur-Energy starts full production operations at Shirley Basin uranium project after Wyoming approval

PUBT·08/10/2026 21:28:30
Listen to the news
Ur-Energy starts full production operations at Shirley Basin uranium project after Wyoming approval
  • Ur-Energy reported full production operations starting at Shirley Basin in late June, positioning it as the largest U.S. ISR uranium producer.
  • Second-quarter drummed output rose to 140,873 lb U3O8; shipments increased to 149,747 lb as Lost Creek ramp-up accelerated.
  • Shirley Basin captured 10,634 lb during limited operations; first resin shipment to Lost Creek for processing expected imminently.
  • Contract deliveries totaled 215,000 lb at an average price of $66.85 per lb, generating $14.4 million in revenue.
  • Unrestricted cash was $95.3 million at June 30; finished inventory at the conversion facility ended at 348,292 lb.


Disclaimer: This news brief was created by Public Technologies (PUBT) using generative artificial intelligence. While PUBT strives to provide accurate and timely information, this AI-generated content is for informational purposes only and should not be interpreted as financial, investment, or legal advice. Ur-Energy Inc. published the original content used to generate this news brief on August 10, 2026, and is solely responsible for the information contained therein.