Lion Copper & Gold targets Q1 2027 completion for Yerington Copper project feasibility study

PUBT·08/10/2026 13:16:19
Listen to the news
Lion Copper & Gold targets Q1 2027 completion for Yerington Copper project feasibility study
  • Lion Copper & Gold reported progress on the Definitive Feasibility Study for the Yerington Copper Project in Nevada, targeting completion in Q1 2027.
  • Stage 3 work under the Nuton earn-in remained on schedule and on budget, with Nuton funding up to about USD 31 million.
  • Completed hydrogeological drilling, geotechnical drilling, and VLT resource drilling, supporting mine design and engineering inputs for the study.
  • Major infrastructure packages moved into third-party bidding, aimed at tightening capital cost estimates in the DFS.
  • Permitting advanced in parallel through baseline environmental work and agency engagement to support future state and federal applications.


Disclaimer: This news brief was created by Public Technologies (PUBT) using generative artificial intelligence. While PUBT strives to provide accurate and timely information, this AI-generated content is for informational purposes only and should not be interpreted as financial, investment, or legal advice. Lion Copper and Gold Corp. published the original content used to generate this news brief via Newsfile (Ref. ID: 202608100915NEWSFILECNPR____20260810_308824_1) on August 10, 2026, and is solely responsible for the information contained therein.