White Gold posts PEA with after-tax NPV(5%) of C$ 1.91 billion for Yukon project

PUBT·08/10/2026 11:08:10
Listen to the news
White Gold posts PEA with after-tax NPV(5%) of C$ 1.91 billion for Yukon project
  • White Gold released a maiden PEA for the White Gold Project in Yukon, outlining a 9.4-year, 12,000-tpd open-pit mine plan.
  • Base case at US$ 3,600/oz: after-tax NPV(5%) C$ 1.91 billion, IRR 38%, payback 1.7 years; initial capex C$ 1.05 billion.
  • Gold price sensitivity at US$ 4,500/oz: after-tax NPV(5%) C$ 3 billion, IRR 52%, payback 1.3 years.
  • Average production 188,000 oz/year over life of mine, 223,000 oz/year in years 1-5; life-of-mine AISC US$ 1,480/oz.
  • PEA mine plan covers four deposits, processing 41 million tonnes at 1.54 g/t Au with 87% average recovery.


Disclaimer: This news brief was created by Public Technologies (PUBT) using generative artificial intelligence. While PUBT strives to provide accurate and timely information, this AI-generated content is for informational purposes only and should not be interpreted as financial, investment, or legal advice. White Gold Corp. published the original content used to generate this news brief via Newsfile (Ref. ID: 202608100700NEWSFILECNPR____20260810_308830_1) on August 10, 2026, and is solely responsible for the information contained therein.