QUESTERRE ENERGY: The heating furnace pipeline at the PX energy facility has seriously broken. The shutdown is expected to continue for three to four weeks, causing loss of production and loss of revenue. The direct cost of the rectification work is estimated at $1.5 million.

Zhitongcaijing·07/31/2026 20:41:13
Listen to the news
QUESTERRE ENERGY: The heating furnace pipeline at the PX energy facility has seriously broken. The shutdown is expected to continue for three to four weeks, causing loss of production and loss of revenue. The direct cost of the rectification work is estimated at $1.5 million.