EnBW hoists two 74-ton sludge dryers into Walheim sewage sludge CHP plant build-out

PUBT·07/24/2026 12:07:49
Listen to the news
EnBW hoists two 74-ton sludge dryers into Walheim sewage sludge CHP plant build-out
  • EnBW advanced its Walheim sewage sludge combined heat and power plant with installation of two 74-ton disc dryers.
  • Facility targets processing 180,000 tons of dewatered sewage sludge per year, shifting the site from former coal generation.
  • Plant designed to supply up to 4 MW of district heat, roughly enough for 300 households in Walheim and nearby areas.
  • Project positions the site for Germany’s 2029 requirement to recover phosphorus from sewage sludge, supporting dedicated mono-incineration capacity.


Disclaimer: This news brief was created by Public Technologies (PUBT) using generative artificial intelligence. While PUBT strives to provide accurate and timely information, this AI-generated content is for informational purposes only and should not be interpreted as financial, investment, or legal advice. EnBW - Energie Baden-Württemberg AG published the original content used to generate this news brief on July 24, 2026, and is solely responsible for the information contained therein.