China Shenhua says Dingzhou Phase III, Cangdong Phase III No. 6 units enter commercial operation after trial run

PUBT·07/23/2026 12:46:15
Listen to the news
China Shenhua says Dingzhou Phase III, Cangdong Phase III No. 6 units enter commercial operation after trial run
  • China Shenhua reported No. 6 units at Dingzhou Phase III and Cangdong Phase III passed 168-hour trials, entered commercial operation.
  • Full operation expected to supply about 11.9 billion kWh of electricity annually, heating output about 20.14 million GJ.
  • Trial runs met ultra-low air pollutant emissions targets, recorded zero wastewater discharge.


Disclaimer: This news brief was created by Public Technologies (PUBT) using generative artificial intelligence. While PUBT strives to provide accurate and timely information, this AI-generated content is for informational purposes only and should not be interpreted as financial, investment, or legal advice. CSEC - China Shenhua Energy Company Ltd. published the original content used to generate this news brief via IIS, the regulatory disclosure system operated by the Hong Kong Stock Exchange (HKex) (Ref. ID: HKEX-EPS-20260723-12254679), on July 23, 2026, and is solely responsible for the information contained therein.