Eldorado Gold crushes first ore at Skouries copper-gold project in Greece

PUBT·07/20/2026 21:07:38
Listen to the news
Eldorado Gold crushes first ore at Skouries copper-gold project in Greece
  • Eldorado Gold reported first ore crushed at its Skouries copper-gold project in northern Greece, marking the start of staged commissioning.
  • First copper-gold concentrate remains targeted for Q3 2026; commercial production is targeted for Q4 2026.
  • Full site energization still depends on final testing, inspection, metering installation, and sign-off by the Greek power authority.
  • Interim generators were added to support commissioning while grid energization is pending; full integrated plant operation requires grid power.
  • Run-of-mine ore stockpiles reached about 3.9 million tonnes, intended to cover plant feed through 2026 and support ramp-up.


Disclaimer: This news brief was created by Public Technologies (PUBT) using generative artificial intelligence. While PUBT strives to provide accurate and timely information, this AI-generated content is for informational purposes only and should not be interpreted as financial, investment, or legal advice. Eldorado Gold Corporation published the original content used to generate this news brief on July 20, 2026, and is solely responsible for the information contained therein.