Blossom Gold begins reopening Portal 2 at Rosebud mine project in Nevada

PUBT·07/16/2026 10:01:32
Listen to the news
Blossom Gold begins reopening Portal 2 at Rosebud mine project in Nevada
  • Blossom Gold began reopening Portal #2 at the Rosebud project in Nevada to restore underground access for drilling and development work.
  • Earthworks started July 7. Portal opening targeted for the week of July 20. Rehabilitation then starts to reach Decline #2.
  • About 3,000 feet of rehabilitation is planned. Completion targeted for late October to support drill-bay construction.
  • Underground infill drilling aimed at upgrading the open-pit resource is slated to start in Q4 2026, supporting a mineral resource update in Q1 2027.
  • Work scope includes bulk sampling for metallurgical testing. The contractor is Small Mine Development.


Disclaimer: This news brief was created by Public Technologies (PUBT) using generative artificial intelligence. While PUBT strives to provide accurate and timely information, this AI-generated content is for informational purposes only and should not be interpreted as financial, investment, or legal advice. Blossom Gold Inc. published the original content used to generate this news brief via GlobeNewswire (Ref. ID: 202607160600PRIMZONEFULLFEED9763087) on July 16, 2026, and is solely responsible for the information contained therein.