Highlander Silver updates Corani Peru silver project as substation construction advances

PUBT·07/07/2026 10:02:10
Listen to the news
Highlander Silver updates Corani Peru silver project as substation construction advances
  • Highlander Silver released a July 7, 2026 photo update highlighting site development progress at its Corani Silver Project in Peru.
  • Workforce exceeded 300, with construction underway on the camp and core facilities.
  • Earthworks started for site infrastructure, pits, and water collection ponds.
  • Internal road rehabilitation progressed; external access road construction advanced.
  • Substation construction continued; transmission line work slated to start in August, with long-lead equipment orders planned for August.


Disclaimer: This news brief was created by Public Technologies (PUBT) using generative artificial intelligence. While PUBT strives to provide accurate and timely information, this AI-generated content is for informational purposes only and should not be interpreted as financial, investment, or legal advice. Highlander Silver Corp. published the original content used to generate this news brief via GlobeNewswire (Ref. ID: 202607070600PRIMZONEFULLFEED9757965) on July 07, 2026, and is solely responsible for the information contained therein.