Galaxy Digital completes Helios Phase I, delivers 133 MW IT load to CoreWeave under 15-year lease

PUBT·07/06/2026 20:32:20
Listen to the news
Galaxy Digital completes Helios Phase I, delivers 133 MW IT load to CoreWeave under 15-year lease
  • Galaxy completed Phase I of its Helios data center campus in West Texas, delivering about 200 MW gross power, including 133 MW of critical IT load, to CoreWeave.
  • Phase I rent under the 15-year lease began in Q2 2026, marking Helios’s shift to revenue-generating operations across the full 133 MW IT load.
  • Phase II greenfield build targets 260 MW of critical IT load, with first data hall deliveries expected in H1 2027.
  • CoreWeave committed to 526 MW of critical IT load across Phases I-III, covering the full 800 MW of gross power contracted at Helios; average annual revenue expected to exceed USD 1 billion.
  • Total approved campus power capacity expanded to 1.63 GW, with potential to scale to 3.6 GW.


Disclaimer: This news brief was created by Public Technologies (PUBT) using generative artificial intelligence. While PUBT strives to provide accurate and timely information, this AI-generated content is for informational purposes only and should not be interpreted as financial, investment, or legal advice. Galaxy Digital Inc. published the original content used to generate this news brief via PR Newswire (Ref. ID: TO98655) on July 06, 2026, and is solely responsible for the information contained therein.