TeraWulf acquires 1+ GW Eastern Kentucky AI, HPC data center development site

PUBT·05/26/2026 12:04:52
Listen to the news
TeraWulf acquires 1+ GW Eastern Kentucky AI, HPC data center development site
  • Terawulf acquired a hyperscale high-performance computing development site in Eastern Kentucky, branded the Muskie Data Campus.
  • Site is expected to support more than 1 GW of data center capacity over time.
  • Initial 500 MW is slated to ramp in 2H 2028; another 500 MW is targeted for 2H 2030.
  • Campus sits within the 1,000-acre EastPark Industrial Park, with about 285 acres owned or controlled for development.
  • Kentucky Power is building a 345 kV substation tied to an existing 765 kV network to support long-term power delivery.


Disclaimer: This news brief was created by Public Technologies (PUBT) using generative artificial intelligence. While PUBT strives to provide accurate and timely information, this AI-generated content is for informational purposes only and should not be interpreted as financial, investment, or legal advice. Terawulf Inc. published the original content used to generate this news brief on May 26, 2026, and is solely responsible for the information contained therein.