Namib Minerals says How Mine mill expansion remains on track for H2 2026 completion

PUBT·06/02/2026 21:26:02
Listen to the news
Namib Minerals says How Mine mill expansion remains on track for H2 2026 completion
  • Namib Minerals reported progress on the How Mine mill expansion to lift processing capacity and support higher gold output.
  • Civil works advanced, with the raft foundation, mill plinth, and tower foundations completed.
  • Key mechanical equipment has arrived on site, including the mill shell; power equipment has completed factory acceptance tests.
  • Construction and commissioning remain targeted for H2 2026.


Disclaimer: This news brief was created by Public Technologies (PUBT) using generative artificial intelligence. While PUBT strives to provide accurate and timely information, this AI-generated content is for informational purposes only and should not be interpreted as financial, investment, or legal advice. Namib Minerals published the original content used to generate this news brief via EDGAR, the Electronic Data Gathering, Analysis, and Retrieval system operated by the U.S. Securities and Exchange Commission (Ref. ID: 0001213900-26-064298), on June 02, 2026, and is solely responsible for the information contained therein.