According to the Zhitong Finance App, CGN Power (01816) issued an announcement. According to the company's statistics, from January to December 2025, the total power generation capacity of nuclear power units operated and managed by the Group was about 247.013 billion kilowatt-hours, an increase of 2.00% over the same period last year. The total feed-in electricity capacity was approximately 232,648 million kilowatt-hours, an increase of 2.36% over the same period last year.
In the fourth quarter of 2025, the Group completed 4 annual material replacement overhauls as planned.
As of December 31, 2025, the Group has completed 16 annual overhauls (including 1 annual New Year's Eve overhaul), 2 10-year overhauls, and 1 initial overhaul as planned.
In the first quarter of 2026, in addition to continuing the material replacement overhaul that has already begun, the Group plans to carry out 4 new annual material replacement overhauls and 3 10-year overhauls.
On November 18, 2025, full construction of Zhaoyuan Unit 1 began and entered the civil construction phase.
On November 19, 2025, Cangnan Unit 3 began full construction and entered the civil construction phase.
On December 16, 2025, complete construction of Ningde Unit 6 began and entered the civil construction phase.
On December 22, 2025, Lufeng Unit 2 began full construction and entered the civil construction phase.
As of December 31, 2025, the Group has managed a total of 20 nuclear power units under construction (including 4 units managed by the Company's controlling shareholder). 4 units are in the commissioning stage, 2 are in the equipment installation stage, 7 are in the civil construction phase, and 7 are in the FCD preparation stage.