Artemis Gold targets Q4 2026 commissioning for $120 million Blackwater Phase 1A expansion

PUBT·08/04/2026 10:51:14
語音播報
Artemis Gold targets Q4 2026 commissioning for $120 million Blackwater Phase 1A expansion
  • Artemis Gold reported Phase 1A expansion work at the Blackwater Mine was 57% complete at end-Q2 2026.
  • Project lifts processing capacity 33% to 8 Mtpa from 6 Mtpa, targeting commissioning in Q4 2026.
  • Expected capital cost set at $120 million, reflecting $60 per added annual tonne of processing capacity.
  • Mine plan and resource model updates are underway in 2026; 2027 production and cost guidance due in early Q1 2027.


Disclaimer: This news brief was created by Public Technologies (PUBT) using generative artificial intelligence. While PUBT strives to provide accurate and timely information, this AI-generated content is for informational purposes only and should not be interpreted as financial, investment, or legal advice. Artemis Gold Inc. published the original content used to generate this news brief on August 04, 2026, and is solely responsible for the information contained therein.