Amex Gold Mining advances Perron underground ramp to 200 meters

PUBT·11/19/2026 12:10:12
Diffusion vocale
Amex Gold Mining advances Perron underground ramp to 200 meters
  • Amex Gold Mining completed 200 meters of underground ramp development at its wholly owned Perron gold project near Normétal, Québec.
  • Ramp development remains on schedule toward the fully funded 40,000-tonne bulk sample program.
  • Construction began on an approximately 6.5-kilometer, 25-kV power line designed to provide about 3 MW of capacity.
  • The connection will support bulk sampling and planned Phase 1 mining operations, reducing reliance on diesel generation.
  • The mechanical garage structure is complete; the permanent underground ventilation system has been installed.


Disclaimer: This news brief was created by Public Technologies (PUBT) using generative artificial intelligence. While PUBT strives to provide accurate and timely information, this AI-generated content is for informational purposes only and should not be interpreted as financial, investment, or legal advice. Amex Gold Mining Inc. published the original content used to generate this news brief via Newsfile (Ref. ID: 202611190700NEWSFILECNPR____20261119_324853_1) on November 19, 2026, and is solely responsible for the information contained therein.