Namib Minerals Says Expanded Milling Plant At How Mine Is Now Operating At Its Full Rate Of ~55,000 Tonnes Per Month

Benzinga·10/26/2026 13:04:02
Diffusion vocale

Ramp-up completed well ahead of the six-to-eight-week timeline and the end-of-December target

NEW YORK, Oct. 26, 2026 (GLOBE NEWSWIRE) -- Namib Minerals ("Namib" or "the Company") (NASDAQ:NAMM), today announced that the expanded milling plant at How Mine has been commissioned and is now operating at its full rate of approximately 55,000 tonnes per month.

As disclosed in the Company’s first-half 2026 results on October 1, 2026, commissioning was expected in mid-October, followed by a ramp-up of approximately six to eight weeks, with the plant expected to reach its full rate by the end of December 2026.