Redeia says Spain-Ceuta power interconnection enters service, enabling instant backup supply

PUBT·09/21/2026 16:32:09
Diffusion vocale
Redeia says Spain-Ceuta power interconnection enters service, enabling instant backup supply
  • Redeia reported the mainland Spain–Ceuta power interconnection is fully energized and in service, providing instant backup for Ceuta’s demand.
  • Transmission grid works run by Red Eléctrica finished in December 2025; the first circuit was energized on March 13, 2026.
  • Distribution facilities were first energized on June 30, 2026; synchronization tests were completed on July 22.
  • The permanent connection was completed on Aug. 10, enabling supply support from the Iberian and broader European system.
  • Commercial electricity exchange scheduling is set to start on Nov. 1 under a decree published on June 30, 2026.


Disclaimer: This news brief was created by Public Technologies (PUBT) using generative artificial intelligence. While PUBT strives to provide accurate and timely information, this AI-generated content is for informational purposes only and should not be interpreted as financial, investment, or legal advice. Redeia Corporación SA published the original content used to generate this news brief on September 21, 2026, and is solely responsible for the information contained therein.