  • Biofrigas customer Långhult Biogas secured a permit to handle flammable materials at the Habo project, enabling work to complete its permanent fueling station.
  • The permit covers the existing installation and the permanent fueling station under Habo phase 2, including a 10-cubic-meter storage tank.
  • An independent inspection is planned for February 2027 before commissioning begins, with customer handover planned alongside the inspection.
  • Commissioning is expected to finish in the first quarter of 2027, completing the Habo facility under the current project plan.


Disclaimer: This news brief was created by Public Technologies (PUBT) using generative artificial intelligence. While PUBT strives to provide accurate and timely information, this AI-generated content is for informational purposes only and should not be interpreted as financial, investment, or legal advice. Biofrigas Sweden AB (publ) published the original content used to generate this news brief via Cision (Ref. ID: 202610230315BITN____UKPR__SV_20261023-BIT-8965-0) on October 23, 2026, and is solely responsible for the information contained therein.