-+ 0.00%
-+ 0.00%
-+ 0.00%

Zhongmin Energy announced that the holding subsidiary Fujian Fuzhou Mintou Offshore Wind Power Junction Station Co., Ltd. and the consortium officially signed the “EPC General Contract for the Changle Offshore Centralized and Unified Delivery Project”. The total contract price is RMB 4.165 billion. The planned construction period is December 31, 2026. The planned grid-connected operation time is December 31, 2028, and the construction period is 731 days.

智通财经·09/28/2026 08:57:23
语音播报
Zhongmin Energy announced that the holding subsidiary Fujian Fuzhou Mintou Offshore Wind Power Junction Station Co., Ltd. and the consortium officially signed the “EPC General Contract for the Changle Offshore Centralized and Unified Delivery Project”. The total contract price is RMB 4.165 billion. The planned construction period is December 31, 2026. The planned grid-connected operation time is December 31, 2028, and the construction period is 731 days.