Webuild starts TBM excavation of 4.4-km Melito tunnel on Naples-Bari high-speed rail line

PUBT·09/25/2026 13:54:32
语音播报
Webuild starts TBM excavation of 4.4-km Melito tunnel on Naples-Bari high-speed rail line
  • Webuild started boring the 4.4-km Melito tunnel on the Naples–Bari high-speed rail line using the 12.5-meter “Aurora” TBM.
  • The tunnel is part of the Apice–Hirpinia lot, an 18.7-km section with about 13 km in tunnels.
  • Work follows completion of the 6.5-km Rocchetta tunnel in May, built in 18 months with the “Futura” TBM.
  • The Naples–Bari program includes 145 km of new railway, part of the TEN-T Scandinavian–Mediterranean corridor.
  • Webuild’s southern Italy backlog totals more than EUR 16 billion across 21 projects, employing 10,300 people.


Disclaimer: This news brief was created by Public Technologies (PUBT) using generative artificial intelligence. While PUBT strives to provide accurate and timely information, this AI-generated content is for informational purposes only and should not be interpreted as financial, investment, or legal advice. Webuild S.p.A. published the original content used to generate this news brief on September 25, 2026, and is solely responsible for the information contained therein.