PTPP nears completion of Rp 1.46 trillion Kataraja toll road section at 94.9%

PUBT·09/08/2026 03:34:07
语音播报
PTPP nears completion of Rp 1.46 trillion Kataraja toll road section at 94.9%
  • PTPP lifted completion of the Kataraja Toll Road Section 1 (STA 0+000–6+700) to 94.9%, targeting completion by Oct. 14, 2026.
  • The contract is valued at IDR 1.46 trillion, excluding VAT.
  • A load test on the Ramp 1 bridge at the Sedyatmo junction was completed on Aug. 27–29, 2026.
  • The section has been operational since Oct. 9, 2025, serving traffic between Jakarta, Soekarno-Hatta airport, and the PIK 2 area.


Disclaimer: This news brief was created by Public Technologies (PUBT) using generative artificial intelligence. While PUBT strives to provide accurate and timely information, this AI-generated content is for informational purposes only and should not be interpreted as financial, investment, or legal advice. PT Pembangunan Perumahan (Persero) Tbk published the original content used to generate this news brief via Indonesia Stock Exchange (IDX) (Ref. ID: 32146046) on September 08, 2026, and is solely responsible for the information contained therein.