Montage Gold targets Koné first gold pour in Q4 2026, says construction ahead of schedule

PUBT·08/11/2026 10:01:39
语音播报
Montage Gold targets Koné first gold pour in Q4 2026, says construction ahead of schedule
  • Montage Gold reported Koné construction remained on budget, targeting first gold pour in Q4 2026 via the oxide circuit.
  • Capital committed reached USD 714.4 million, about 81% of the USD 885 million upfront capex estimate; USD 161.2 million remained for oxide completion.
  • Total liquidity and Koné funding sources totaled USD 309 million, exceeding remaining project capital disbursements of USD 261.2 million.
  • Dry commissioning started following grid-power connection; mining began to build a four-week run-of-mine stockpile for oxide start-up.
  • Exploration drilling expanded to 130,000 meters at Koné in 2026; additional 85,000 meters planned at Didievi.


Disclaimer: This news brief was created by Public Technologies (PUBT) using generative artificial intelligence. While PUBT strives to provide accurate and timely information, this AI-generated content is for informational purposes only and should not be interpreted as financial, investment, or legal advice. Montage Gold Corp. published the original content used to generate this news brief via GlobeNewswire (Ref. ID: 202608110600PRIMZONEFULLFEED9807592) on August 11, 2026, and is solely responsible for the information contained therein.