TAESA says ONS clears Ananaí energization, adding about R$ 123.6 million to permitted annual revenue

PUBT·08/04/2026 22:21:21
语音播报
TAESA says ONS clears Ananaí energization, adding about R$ 123.6 million to permitted annual revenue
  • TAESA reported ONS clearance to energize Ananaí’s 500 kV Ponta Grossa–Assis C1 and C2 transmission lines.
  • The move adds about R$ 123.6 million to 2026-2027 permitted annual revenue, effective retroactively from July 27, 2026.
  • Total enabled 2026-2027 revenue for Ananaí now stands near R$ 168.7 million, representing 97.3% of the project’s total RAP.
  • Ananaí’s total 2026-2027 RAP is R$ 173.3 million; ANEEL capex is R$ 1.75 billion; the project is 100% TAESA-controlled.
  • Start-up came 8-10 months ahead of the March 2027 regulatory deadline, strengthening power interchange across Brazil’s South, Southeast, Center-West.


Disclaimer: This news brief was created by Public Technologies (PUBT) using generative artificial intelligence. While PUBT strives to provide accurate and timely information, this AI-generated content is for informational purposes only and should not be interpreted as financial, investment, or legal advice. TAESA - Transmissora Aliança de Energia Elétrica SA published the original content used to generate this news brief on August 04, 2026, and is solely responsible for the information contained therein.