NextDecade targets first LNG from Rio Grande Train 1 in H1 2027

PUBT·07/30/2026 11:46:41
语音播报
NextDecade targets first LNG from Rio Grande Train 1 in H1 2027
  • NextDecade kept guidance for first LNG from Rio Grande LNG Train 1 in H1 2027; first gas expected in H2 2026.
  • Construction on Trains 1-5 ran ahead of schedule and within budget; Trains 1-2 reached 74% overall completion by June.
  • Train 6 expansion advanced with a FERC application; final Environmental Impact Statement scheduled for June 25, 2027.
  • Train 6 timeline supports a final investment decision target in H2 2027; reservation agreement signed with Baker Hughes for compressors.
  • Project financing shifted to longer-dated debt, including USD 3.5 billion senior secured notes; Phase 1 HoldCo added a USD 1 billion term loan.


Disclaimer: This news brief was created by Public Technologies (PUBT) using generative artificial intelligence. While PUBT strives to provide accurate and timely information, this AI-generated content is for informational purposes only and should not be interpreted as financial, investment, or legal advice. NextDecade Corporation published the original content used to generate this news brief via Business Wire (Ref. ID: 202607300730BIZWIRE_USPR_____20260730_BW544785) on July 30, 2026, and is solely responsible for the information contained therein.