Eni, KazMunayGas start first power output from 120-MW gas unit at Kazakhstan hybrid plant

PUBT·07/22/2026 07:36:46
语音播报
Eni, KazMunayGas start first power output from 120-MW gas unit at Kazakhstan hybrid plant
  • Eni reached first industrial electricity from a 120 MW gas power plant in Kazakhstan’s 247 MW Mangystau hybrid project with KazMunayGas, via Plenitude.
  • The project targets a decarbonized, reliable power supply for KazMunayGas subsidiaries, combining solar generation, gas output, future wind capacity.
  • A 50 MW solar plant was commissioned in September 2025; final commissioning of the gas plant is targeted in Q3 2026.
  • A 77 MW wind plant is scheduled to start operations in 2027, completing the hybrid configuration.


Disclaimer: This news brief was created by Public Technologies (PUBT) using generative artificial intelligence. While PUBT strives to provide accurate and timely information, this AI-generated content is for informational purposes only and should not be interpreted as financial, investment, or legal advice. Eni S.p.A. published the original content used to generate this news brief on July 22, 2026, and is solely responsible for the information contained therein.