Implenia-led consortium completes lift-in of 1,300-ton midspan for Germany’s Rader High Bridge on A7

PUBT·07/16/2026 12:15:48
语音播报
Implenia-led consortium completes lift-in of 1,300-ton midspan for Germany’s Rader High Bridge on A7
  • Implenia-led consortium completed the central span lift for the replacement Rader High Bridge on Germany’s A7, closing the gap over the Kiel Canal.
  • The 118-meter steel midsection weighs about 1,300 tons; it was transported by pontoon from the Port of Rendsburg for installation.
  • The 1,500-meter, 42-meter-high bridge is being built for DEGES; the project started in 2023 and is expected to finish in late 2026.


Disclaimer: This news brief was created by Public Technologies (PUBT) using generative artificial intelligence. While PUBT strives to provide accurate and timely information, this AI-generated content is for informational purposes only and should not be interpreted as financial, investment, or legal advice. Implenia AG published the original content used to generate this news brief on July 16, 2026, and is solely responsible for the information contained therein.